 Centering and Shuttering for basement retainer wall to fill the concrete mixed with water proofing chemical Sump Bases are ready   Sump Bases are ready  Basement wall now raised up to 3 feet level Curing of the basement foundation and side walls
Image
Beam interconnecting pillars at the basement level
Image
 Concreting of footing completed consumed 100 bags of cement 4 truck loads of Jelly and 3 truck loads of sand Concreting of footing   Cage for sump for rain water harvesting completed Cage for sump for drinking water in progress
Image
Placing of Ankale Kaddi below the pillar which is  a ritual during foundation. 2 will be placed in deva mule, 1 each in agni and kubera mule and 1 in the 4th mule. Deva Mule pre-concreting puja with offering of arasina Deva Mule pre-concreting puja with offering of kunkuma For deva mule pillar Tieing of secred cloth containing vyduriya (nava rathna) pancha loha (gold, silver....) prasad  Offering Puja to deva mule pillar  Offering vilyadele dakshine coconut and banana  Offering prayer to Sun God After the puja the concreting from deva mule started
Image
 Drinking water sump pre-concreting work in progress  Rain water harvesting sump pre-concreting work in progress Last pillar but the strongest pillar ready for erection
Image
 Assembly of Footing  Assembly of pillars  Erection of Pillars into footings More number of pillars erected (total 14 Nos.) Thumb rule 1 pillar per 100 sq. feet of living space
Image
 Pillars are being built  Pillars are built  Pillars are positioned  Footing with pillars errected Multiple footings with pillars in place
Image
Floor plans dated 11.06.2017
Image
3D View Option 03 
Image
 Structural Engineer discussing the marking of footings  Granite stone for retainer walls on east and west side  Footings are getting ready making of footings  is in progress Positioning of footings
Image
 Structural Engineer instructing mestri on the next action plan  Structural engineer and architect discussing blocking of water from storm water drain on the west side  structural engineer discussing with bar bender on the positioning of pillars and footings  Architect watching from top total view of the basement floor 
Image
 Concrete is getting ready by mixing of cement, sand, Jelly and water  Concrete is being poured into trolleys waiting below  Trolley is unloaded for reloading again  Trolleys kept below to receive the concrete  Trolleys with concrete  Trolley with concrete is pushed to different locations The concreting work for basement is started with Deva Mule (North east corner of the plot)