 All pillars are raised to facilitate ground floor wall construction
Image
 Basement North side window space and westside baywindow space  Basement southside window space  Far end is the sitout space 6" above that ground floor starts  Ground floor outside toilet and restroom of ground floor with water filled backyard for gardening 6 feet wide and 40 feet long
Image
 Final inspection by all agencies before pouring concrete to make sure their service lines are in place  Puja is being done before pouring the concrete  Dakshina given to watchman for doing a good job Completion of the mold with this basement is complete & we will start the ground floor week after next
Image
 Basement Lighting Fan AC will be through conduits laid in the ground floor  All services will be centralized in the basement such as UPS, DLNA server, CCTV server Security controls, water level controls, Dish antenna, internet connection, 
Image
 Ground floor Kitchen cum living room as seen from kitchen end  Ground floor kitchen cum living room as seen from living room Height of ground floor as seen from road level
Image
 Outside toilet ready for concreting  Ground floor rest room and bed room ready for concreting  Ground floor to basement staircase ready for concreting Landing place between ground floor and basement with bay window ready window to be placed later